- We built tested and installed a new emergency vent valve to replace the one that got snapped off.
- We finished rewireing the top end of the vehicle.
- We repaired the bent vane mount.
- We modified the motor so we can change catalyst orifice sizes.
We are waiting on several next day parts orders but the tasks for today are:
- Reassemble and calibrate the vane actuators.
- Change the position feedback on the main valve to be more robust and visually verifiable.
- Redo the bottom end wireing
- Buy more Tether (clmbbing rope)
- Replace a damaged battery
- Replace all the battery tie down straps as they were damaged by the peroxide.
- Replace the 1” Peroxide check valve with a 1.5” checkvalve. (One of the parts we are wating for)